  1. Change Order Wiley Easton Construction Contract The Committee recommended Council approval of a $97,377 increase in the Wiley Easton Construction contract.
  2. Easement for SCE&G Pressure Release Station The Committee recommended Council approval of an easement to SCE&G for the installation of a gas regulation station on the Public Works Compound in Ballentine.
  3. Quitclaim Deeds for Woodcreek Development and The Ridge The Committee forwarded this item to Council without recommendation and asked staff to verify the market value for the property for which the quitclaim deeds were requested.